Typical
Tee Area & Concrete Specifications

Concrete Specifications:
1. 4" Minimum
Thickness
2. 3000 PSI Minimum
3. 4" slump (recommended)
4. Approx. 1 cubic yard per each 12' x 6' x 4" tee pad.
5. Use rebar or wire when building on unstable soil.
Finish:
1. Create a
Very Coarse finish! Most broom finishes will wear smooth
within one year and will be ineffective during wet conditions. To
achieve an excellent finish, affix a weighted Astroturf mat to a
broom and drag the mat across the wet concrete. Timing is essential
to the finish. Drag the grass-like blades across the wet surface
shortly after floating but before a broom finish would normally
be applied.
2. Two inch
finished edge (optional)
Grade:
1. The tee pad
should be essentially level from side to side.
2. From front
to back, the pad may slope to follow grade, but slope must not exceed
1 inch per foot. To allow for drainage, the pad should never be
perfectly level or have low areas that will harbor water.
3. Pad elevation
should not interfere with mowing and other maintenance operations.
|